Electrical and energy

PRINCIPALES REFERENCIAS

New substation “La Mayacina” 30/12kV, Mieres
Nueva subestación la mayacina 30/12kv, Mieres

Year:
2007

Client:
TECUNI

Location:
Mieres, Asturias, Spain

Contract cost:
1.675.360,43 €

Services provided:

  • Project

Description:

The substation, as a whole, excepting the access and exit buildings and some other ventilation elements, are located underground.

In this way, the entire substation (transformers, switch gears, cells, control, protection, communication and auxiliary service equipments) is located in an underground building with the following dimensions:

  • 20x30 m Rectangular ground plant.
  • 6 meters maximum height + 1meter extra deep for the layout of power and control cable.

Buscar proyectos

Buscar proyectos

Proyectos relacionados

    Volver a resultados de búsqueda
     
    SUBVENCIÓN PARA LA PROMOCIÓN INTERNACIONAL 2010

  • Presentación y catálogos de la empresa en inglés, francés y portugués
  • Estudios de mercado para Panamá y Argelia
  • 6 Viajes de prospección a Argelia

  • ...